*Kundalahalli Junction: BWSSB Cauvery Water Pipeline Leakage Update*
The 450 mm main pipeline has been repaired in the shortest possible time by a well coordinated effort from BBMP Projects Team, BWSSB and BTP HAL & Whitefield Circle
Restoration upto Wet mix level is done. Concrete also has been poured around the pipe to provide additional barricading to vibrations
The soil below is also very wet because of the huge water leakage. So, we will have to wait for 7-10 days before the Asphalting work can be done
Mahadevapura Task Force
Jal Shakthi and Mobility